FIREFINDER SERIES II INSTALLATION, COMMISSIONING &
OPERATION
19.1.4 Monthly Test
In addition to the Weekly Test specified above, the following Inspection and testing procedures
should be carried out each month:
Simulate fire conditions on alt alarm zones and reset the system to normal. Confirm with the
monitoring station when the test has been completed.
Check battery voltage and charging current in accordance with the manufacturer's
instructions.
Check batteries and their terminals as specified by the manufacturer to ensure that they are
in good serviceable condition. Where applicable, examine to ensure that the specific gravity
and the level of the electrolyte in each cell is correct
Check condition of battery cabinet for corrosion and to ensure that batteries are stored in a
secure condition.
Check to ensure that all indicating lights are operating correctly and replace if faulty.
Check operation of all alarm sounders.
Disconnect the battery supply and ensure that the visual and audible fault signals are
activated at the main alarm panel.
Simulate main power supply failure and ensure that the system will operate correctly with the
standby battery power supply.
Simulate fire alarm conditions and check the output signals available to initiate the remote
auxiliary functions that is required to be in operation in the event of fire as in accordance with
the appropriate codes.
Simulate fault conditions on all alarm zones to ensure that the main alarm panel is operating
correctly.
Check that the main alarm panel is in a clean and operative condition.
Visually inspect the condition of components, terminations and cables.
Ensure that faulty parts are replaced and the replacement has been carried out satisfactorily.
Record in the log book any circuit fault that required repair.
Check that all switches are returned to their operating position after the test.
The person carrying out the test should record in the log any fault(s) identified and that the
above test has been carried out.